Morgan To Whyalla Pipeline No 2 PS

Solar · SA · MWPS2PV1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
6 MW
Intervals limited
7.3%
Curtailed while constrained
0.0 GWh
Other curtailment
0.6 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−76 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
S>>MW2MW3_RBNW1Robertstown to North West Bend 172chargeOut= Morgan Whyalla Pump 2 - Morgan Whyalla Pump 3 132 kV line avoid O/L Robertstown to North West Bend #1 132kV line on trip of Nil, Feedback
I_6F_SN_150Of 150 MW on Bundey46dischargeDiscretionary limit of 150 MW on Bundey to Buronga (6F) 330 kV Line (SA to NSW)
S>>MW2MW3_NWRB1Robertstown to North West Bend 145dischargeOut= Morgan Whyalla Pump 2 - Morgan Whyalla Pump 3 132 kV line avoid O/L North West Bend to Robertstown #1 132kV line on trip of Nil, Feedback
S>>BWMP_TWPA_TPRSManage voltage collapse in northern SA for the trip of one 275kV line42dischargeOut= Blyth West- Munno Para 275kV line with Blyth West CB8002 OPEN, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback
S>>NIL_TWPA_TPRSManage voltage collapse in northern SA for the trip of one 275kV line16dischargeOut= NIL, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback
S>>V_MWP3RB_RBNW1Robertstown to North West Bend 16chargeOut= Morgan Whyalla Pump3 - Robertstown 132kV line, avoid O/L Roberstown-North West Bend 132kV line on trip of Nil trip, Feedback
S>>BWMP_BRTW_WTTPManage voltage collapse in northern SA for the trip of one 275kV line3dischargeOut= Blyth West- Munno Para 275kV line with Blyth West CB8002 OPEN, avoid O/L Waterloo-Templers 132kV line on trip of Brinkworth-Templers West 275kV line, Feedback
S>>BRTW_BWPA_WTTPManage voltage collapse in northern SA for the trip of one 275kV line3dischargeOut= Brinkworth- Templers West 275kV line, avoid O/L Waterloo-Templers 132kV on trip of Blyth West-Munno Para 275kV line, Feedback
S>>V_NIL_NIL_RBNW1Robertstown to North West Bend 12chargeOut = Nil, avoid overloading Robertstown-North West Bend #1 132kV lines for no contingencies, feedback
S>>NIL_RBTU_WEWTWaterloo East-Waterloo2dischargeOut= Nil, avoid O/L Waterloo East-Waterloo 132kV line on trip of one Robertstown-Tungkillo 275kV line, Feedback
S>>NIL_BWMP_WTTPManage voltage collapse in northern SA for the trip of one 275kV line2dischargeOut= Nil, avoid O/L Waterloo - Templers 132kV on trip of Blyth West- Munno Para 275kV line, Feedback
SA_ISLE_STRENGTHManage voltage collapse in northern SA for the trip of one 275kV line1dischargeMaximum limit (1900 MW) for SA non-synchronous generation for system strength requirements when SA is at risk of separation or when islanded (NOTE: This limit applies when 2-4 syn cons are I/S at RB and DV).
S>>CNRB_TWPA_TPRSManage voltage collapse in northern SA for the trip of one 275kV line1dischargeOut= Canowie-Robertstown 275kV line, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback
S>>NIL_RBTX_RBTX_1One Robertstown 275/ TX1chargeOut= Nil, avoid O/L of one Robertstown 275/132kV TX on trip of other Robertstown 275/132kV TX, Feedback
S-MWPS2-PV_0Robertstown to North West Bend 11dischargeDiscretionary upper limit for SA WATER Morgan Whyalla Pump Station 2 PV generation of 0 MW
Showing the 15 constraints with the most hours; 6 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.