| I_6F_SN_150 | Of 150 MW on Bundey | 46 | discharge | Discretionary limit of 150 MW on Bundey to Buronga (6F) 330 kV Line (SA to NSW) |
| S>>BWMP_TWPA_TPRS | Manage voltage collapse in northern SA for the trip of one 275kV line | 42 | discharge | Out= Blyth West- Munno Para 275kV line with Blyth West CB8002 OPEN, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback |
| S>>NIL_TWPA_TPRS | Manage voltage collapse in northern SA for the trip of one 275kV line | 16 | discharge | Out= NIL, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback |
| S>>V_MWP3RB_RBNW1 | Robertstown to North West Bend 1 | 6 | charge | Out= Morgan Whyalla Pump3 - Robertstown 132kV line, avoid O/L Roberstown-North West Bend 132kV line on trip of Nil trip, Feedback |
| S>>BWMP_BRTW_WTTP | Manage voltage collapse in northern SA for the trip of one 275kV line | 3 | discharge | Out= Blyth West- Munno Para 275kV line with Blyth West CB8002 OPEN, avoid O/L Waterloo-Templers 132kV line on trip of Brinkworth-Templers West 275kV line, Feedback |
| S>>BRTW_BWPA_WTTP | Manage voltage collapse in northern SA for the trip of one 275kV line | 3 | discharge | Out= Brinkworth- Templers West 275kV line, avoid O/L Waterloo-Templers 132kV on trip of Blyth West-Munno Para 275kV line, Feedback |
| S>>NIL_RBTU_WEWT | Waterloo East-Waterloo | 2 | discharge | Out= Nil, avoid O/L Waterloo East-Waterloo 132kV line on trip of one Robertstown-Tungkillo 275kV line, Feedback |
| S>>NIL_BWMP_WTTP | Manage voltage collapse in northern SA for the trip of one 275kV line | 2 | discharge | Out= Nil, avoid O/L Waterloo - Templers 132kV on trip of Blyth West- Munno Para 275kV line, Feedback |
| SA_ISLE_STRENGTH | Manage voltage collapse in northern SA for the trip of one 275kV line | 1 | discharge | Maximum limit (1900 MW) for SA non-synchronous generation for system strength requirements when SA is at risk of separation or when islanded (NOTE: This limit applies when 2-4 syn cons are I/S at RB and DV). |
| S>>CNRB_TWPA_TPRS | Manage voltage collapse in northern SA for the trip of one 275kV line | 1 | discharge | Out= Canowie-Robertstown 275kV line, avoid O/L Templers-Roseworthy 132kV line on trip of Templers West-Para 275kV line, Feedback |
| S>>NIL_RBTX_RBTX_1 | One Robertstown 275/ TX | 1 | charge | Out= Nil, avoid O/L of one Robertstown 275/132kV TX on trip of other Robertstown 275/132kV TX, Feedback |
| S>>BRDV_RBTU_WEWT | Waterloo East-Waterloo | 0 | discharge | Out= Brinkworth - Davenport 275kV line, avoid O/L Waterloo East-Waterloo 132kV line on trip of Robertstown-Tungkillo 275kV line 1 or 2, Feedback |
| S>>V_NWRB2_RBNW1 | Robertstown to North West Bend 1 | 0 | charge | Out = North West Bend-Robertstown 132kV No2 line, limit SA-V on ML to avoid O/L of Robertstown-NWB1 132kV line |
| S>>BDBU_RBTU_WEWT | Of 150 MW on Bundey | 0 | discharge | Out= Bundey to Buronga 330kV, avoid O/L Waterloo East-Waterloo 132kV line on trip of one Robertstown-Tungkillo 275kV line, Feedback |
| S>>NIL_BRTW_WTTP | Manage voltage collapse in northern SA for the trip of one 275kV line | 0 | discharge | Out= Nil, avoid O/L Waterloo - Templers 132kV on trip of Brinkworth - Templers West 275kV line, Feedback |