Snowy Pumping

– · NSW · SNOWYP
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
0 MW
Intervals limited
6.4%
Curtailed while constrained
0.0 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−8 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N::N_CNCW_2Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)145chargeOut = Canberra-Capital (6) line, stability limit (Snowy-NSW) for critical fault of one 330kV line between Yass and Bannaby/Marulan
N::N_SDUT_2Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)111chargeOut = Upper Tumut-Stockdill (1) 330kV line, stability limit (Snowy-NSW) for fault of various location between Yass-South Morang area
N^^V_CNCW_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink49dischargeOut = Canberra-Capital (6) or Kangaroo Valley to Capital (3W) or Dapto-Kangaroo Valley (18), avoid voltage collapse at Darlington Point for loss of the largest Vic generating unit or Basslink
N^^V_NIL_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink41dischargeOut = Nil, avoid voltage collapse at Southern NSW for loss of the largest Vic generating unit or Basslink
V>>N_NIL_65_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV34chargeOut = NIL, avoid O/L Murray to Upper Tumut (65) on trip of Wagga to Lower Tumut (051) line, Feedback
V^^N_NIL_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV33chargeOut = Nil, avoid voltage collapse around Murray for loss of all APD potlines
N^^V_MLNK_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink19dischargeOut = Murraylink, avoid voltage collapse at Southern NSW for loss of the largest Vic generating unit or Basslink
V^^N_SDUT_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV11chargeOut = Stockdill to Upper Tumut (1) line, avoid voltage collapse around Murray for loss of all APD potlines
V^^N_BADP_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV10chargeOut = Balranald to Darlington Point (X5) 220kV line, avoid voltage collapse around Murray for loss of all APD potlines
N^^V_BADP_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink10dischargeOut = Balranald to Darlington Point (X5) 220kV line, avoid voltage collapse at Darlington Point for loss of the largest Vic generating unit or Basslink
V^^N_GRYS_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV7chargeOut = Gullen Range to Yass (3J), avoid voltage collapse around Murray for loss of all APD potlines
N^^V_MLNK_ARWBBASouthern NSW: voltage stability for loss of the largest Victorian unit or Basslink7dischargeOut = Murraylink, avoid voltage collapse in southern NSW for loss of Ballarat to Waubra to Ararat 220kV lines (this also trips Waubra, Ararat and Crowlands, Bulgana and Murra Warra WFs)
N^^V_NIL_ARWBBASouthern NSW: voltage stability for loss of the largest Victorian unit or Basslink5dischargeOut = Nil, avoid voltage collapse in southern NSW for loss of Ballarat to Waubra to Ararat 220kV lines (this also trips Waubra, Ararat and Crowlands, Bulgana and Murra Warra WFs)
N::N_GRRP_2Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)4chargeOut = Gullen Range to Rye Park (3P), stability limit (Snowy-NSW) for loss of Yass-Marulan (4/5) 330kV line
N^^V_JNWG_63_X5_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink4dischargeOut = Jindera to Wagga(62) 330kV line, 63 + X5 open, avoid voltage collapse at Southern NSW for loss of the largest Vic generating unit or Basslink
Showing the 15 constraints with the most hours; 8 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.