Wellington North Solar Farm (Lightsource)

Solar · NSW · WELNSF1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
437 MW
Intervals limited
13%
Curtailed while constrained
0.5 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−298 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>94T_947_72Central-west NSW: Molong–Orange North 132 kV119dischargeOut= Molong to Orange North (94T) 132kV line, avoid O/L Wellington to Orange North (947) 132kV line on trip of Wellington to Mt Piper (72) 330kV line, Feedback
N>NIL_945_947Central-west NSW: Molong–Orange North 132 kV69dischargeOut= Nil, avoid O/L Wellington to Wellington Town (945/2) 132kV line on trip of Wellington to Orange North (947) 132kV line, Feedback
N>NIL_94T_72Central-west NSW: Molong–Orange North 132 kV68dischargeOut= Nil, avoid O/L Molong to Orange North (94T) 132kV line on trip of Wellington to Mt Piper (72) 330kV line, Feedback
N>NIL_947_94TCentral-west NSW: Molong–Orange North 132 kV19dischargeOut= Nil, avoid O/L Wellington to Orange North (947) on trip of Molong to Orange North (94T), Feedback
N>NIL_75_WOTX_72Central-west NSW: Molong–Orange North 132 kV8dischargeOut= Nil, avoid O/L Wollar West - Wollar (75) 330kV line or Wollar 330/500kV transformer on trip of Wellington to Mt Piper (72) 330kV line, Feedback
N>>NIL_33_34Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to6dischargeOut= Nil, avoid Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to Liddell (34 or 33), Feedback
N>72_94T_75Molong to Orange North (94T)5dischargeOut = Mt Piper to Wellington line (72), avoid O/L Molong to Orange North (94T) on trip of Wollar West to Wollar (75) line, Feedback
N>NIL_94T_75Central-west NSW: Molong–Orange North 132 kV4dischargeOut= Nil, avoid O/L Molong to Orange North (94T) 132kV line on trip of Wollar West to Wollar (75) 330 kV line, Feedback
N>>33_34_QMAX_NBayswater to Liddell (33 or 34) O/L on loss of other Bayswater to3dischargeOut = Bayswater to Liddell(33 or 34), avoid O/L Bayswater to Liddell(33 or 34) on trip of QLD largest generation, Feedback
N>>34+5A5_33_32Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to2dischargeOut= Mt. Piper-Wollar (5A5) and Bayswater to Liddell (33 or 34) line, avoid O/L Bayswater to Liddell (33 or 34) 330kV line on trip of Bayswater to Sydney West (32) 330kV line, Feedback
N>5A4_94T_5A5Central-west NSW: Molong–Orange North 132 kV1dischargeOut = Bayswater to Wollar (5A4) 500kV line, avoid O/L Molong to Orange North (94T) 132kV line on trip of Wollar to Mt Piper (5A5) 500kV line, Feedback
N>945+94M_947_72Molong to Orange North (94T)1dischargeOut= Beryl to Crudine Ridge 132kV line (94M) and Molong to Wellington 132kV line (945) , avoid O/L Wellington to Orange North (947) 132kV line on trip of Mt Piper to Wellington (72) 330kV line, Feedback
CA_BRIS_59CD80D1_1Molong to Orange North (94T)1dischargeConstraint Automation, O/L 947:L947:I:132@WELLNGTN@NSW for CTG LNQR on trip of WELLNGTN-MT_PIPER 72 330KV LN. Generated by STNET[NORCR1] Host BNEREGEEMP5(EMPBRI)
N>>945_947_72Molong to Orange North (94T)1dischargeOut= Wellington to Molong 132kV line (945), avoid O/L Wellington to Orange North (947) 132kV line on trip of Wellington to Mt Piper (72) 330kV line, Feedback
N>9ML_947_94TCentral-west NSW: Molong–Orange North 132 kV1dischargeOut= 9ML (Mt Piper to Crudine Ridge tee Ilford), avoid O/L Wellington to Orange North (947) on trip of Molong to Orange North (94T), Feedback
Showing the 15 constraints with the most hours; 1 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.