Yallourn W

Coal · VIC · YWPS1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
350 MW
Intervals limited
0.0%
Curtailed while constrained
0.0 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−37 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
V::N_NIL_V1Victoria: transient stability, Hazelwood–South Morang 500 kV15chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV.
V::N_KGRC_V1Victoria: transient stability, Hazelwood–South Morang 500 kV11chargeOut = Kerang to Red Cliffs 220kV line (or any section in between), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV.
V::N_KGRC_O1Victoria: transient stability, Hazelwood–South Morang 500 kV3chargeOut = Kerang to Red Cliffs 220kV line (or any section in between), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, Other than VIC accelerates. Yallourn W G1 on 220kV.
V::N_NIL_O1Victoria: transient stability, Hazelwood–South Morang 500 kV0chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, Other than VIC accelerates. Yallourn W G1 on 220kV.
V>>SMF2_SMF1_NIL_R5The remaining South Morang 500/ F transformer0dischargeOut = South Morang 500/330kV F2 transformer, avoid pre-contingent O/L of the remaining South Morang F1 500/330kV transformer, radial mode, YWPS unit 1 on 500kV, feedback
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.